Sign Company · 7 min read
A monument sign at the property entrance: survey, permit, foundation and install in Dallas
A monument sign is a small construction project, not a print job. Here is the order the work happens in, what the City of Dallas asks for, and where the schedule usually slips.
What does it take to get a monument sign in Dallas?
A monument sign takes a site survey, a design everyone approves, a City of Dallas sign permit pulled by a registered contractor, fabrication, a foundation and, if it lights up, electrical work. I treat it as a small construction project. The permit itself can be quick; design decisions and approvals take most of the time.
I run the FASTSIGNS center on North Jim Miller Road near Fair Park, and monument and directional signs are part of the exterior work we design, produce and install. Most owners who ask about a monument sign have a building set back from the road, behind parking or among several tenants, where a wall sign is hard to see from passing traffic.
This guide walks through the steps in the order they happen, what the city asks for, and the decisions that keep a project on schedule.
Is a monument sign the right sign for your property?
A monument sign is usually right when drivers need to find your entrance before they see your building. FASTSIGNS describes monument signs as sturdy signs made of dimensional letters or a cabinet, permanently fixed to the ground by a solid base, and they can be lit or unlit.
If your storefront faces the street and sits close to the sidewalk, channel letters or a cabinet on the wall may do more for less. I compare those options in my guide to channel letters, cabinet signs and dimensional letters. A monument sign earns its place on properties with a long driveway, a deep parking lot, a multi-tenant site or an office campus where several entrances look alike.
Before going further, confirm you control the spot. On a leased property, the landlord or the property manager usually decides whether a freestanding sign is allowed, where it goes and what it looks like.
Step one: the site survey
Every monument sign starts with a visit to the property. Our center's survey and permitting service exists for this: we perform the survey and procure the permits the sign needs, so the design starts from the real site, not a guess from a satellite photo.
On a survey, I look at the items that change the design or the price:
I also stand where customers actually turn in and look back at the planned spot. A location that looks perfect on a site plan can be blocked by a parked delivery truck, a utility box or a neighbor's tree. Moving the sign a few feet at this stage costs nothing; moving it after the foundation is poured costs a great deal.
- Where the property line and any right-of-way sit relative to the planned spot.
- What drivers see from both directions, and from how far away.
- Existing signs on the property, including any other freestanding sign on the same street frontage.
- Underground utilities, irrigation lines and tree roots near the location.
- Whether power is already nearby or has to be brought out for a lit sign.
- Slope, drainage and the landscaping the sign will sit in.
What rules does Dallas apply to monument signs?
Dallas requires a sign permit for any new or re-faced sign that has an effective area over 20 square feet, is over eight feet tall, is illuminated or has electrical components, sits in or over a public roadway, or is in a Special Provision Sign District. Most monument signs meet at least one of those conditions.
The City of Dallas sign page also sets out detached sign rules. It describes a monument sign as having no gap between the sign and the ground, lists setbacks that depend on whether the property has a single tenant, and says each street frontage is generally limited to one detached sign. Detached signs on the same premises have to be spaced apart, and non-business zoning districts have tighter size limits.
Special Provision Sign Districts are overlays with their own rules, and the city notes some may require special or additional review. Check whether your property is in one before you approve a design. The city also requires an approved Certificate of Occupancy for the business the sign advertises before a sign permit is approved.
Step two: design and approvals
Design starts with what the sign has to do: show the business name to a driver at speed, match the building and the brand, and hold up outdoors for years. I usually show the design on a photo of the actual site, so owners and landlords can judge size and placement before anything is built.
This is the step where schedules slip most. A landlord may want changes to colors, materials or tenant panels. An owner may decide halfway through to add lighting. Every round of changes adds time before the permit application can be prepared.
Readability matters more than decoration. A driver passing an entrance has a few seconds, so the business name should be the largest element, with strong contrast between the letters and the background. Taglines, phone numbers and long lists of services rarely survive that test and usually belong on the building or the website instead.
Decisions to settle at this stage include the base material, lit or unlit, single-sided or double-sided, a fixed name or changeable tenant panels, and whether the address number belongs on the sign. Each choice also moves the price, which I explain in my guide on what drives the price of a business sign in Dallas.
How long does a Dallas sign permit take?
The City of Dallas says sign permits typically take about two business days when all required items are submitted. Incomplete applications, or a property inside a Special Provision Sign District, take longer.
The city states that a contractor must be registered before any sign permit can be issued, and that electrical sign installation requires a registered electrical or sign electrical contractor. The city publishes a separate prescreen checklist with the complete list of items needed for sign permit review, and we work from it when we prepare a submission.
Owners sometimes assume the permit is the bottleneck. In my experience it rarely is, as long as the paperwork is complete and the business already has its Certificate of Occupancy.
Overall, the schedule for a monument sign is driven by how quickly the owner and landlord decide on the design, how complex the fabrication is and whether electrical work is needed. When I give a timeline, I break it into those pieces so you can see which ones depend on your decisions and which depend on us.
Step three: fabrication, foundation and power
Once the design is approved and the permit is issued, the sign goes into production. Fabrication time depends on the sign: a simple cabinet on a base moves faster than a design with routed letters, custom metal and internal lighting.
While the sign is being built, the site is prepared. A monument sign needs a stable base sized for the sign and the soil, and North Texas clay that swells and shrinks with moisture is one reason I do not cut corners there. Utility locates should be done before anyone digs.
For a lit sign, power has to reach the location. FASTSIGNS International notes that it does not perform electrical sign work, and each independently owned center follows local licensing and code requirements for electrical work. On a property where new service or a dedicated circuit is needed, a commercial electrician belongs in the plan early; an electrician's guide to what a business owner should settle before electrical work starts is a useful read.
Installation day and the weeks after
Installation usually means setting the sign on its base, anchoring it, finishing the trim around the bottom and, for lit signs, making the final connection and testing the lights at dusk. Landscaping around the base is often the last step and is worth planning, because a monument sign buried behind shrubs in two years loses its job.
After installation, schedule a quick look at the sign at night and after the first heavy rain. Lights that flicker, water pooling at the base or soil settling around it are easier to deal with in the first weeks.
A monument sign also needs simple upkeep. Keep sprinklers from spraying the sign face, trim plants that start to cover the lettering, and wipe dust and pollen from the faces a few times a year. Replacing a faded tenant panel or a failed light early keeps the whole sign looking cared for.
Mistakes that delay monument sign projects
Most delays I see come from decisions made out of order. The common ones:
- Ordering a design before confirming the landlord allows a freestanding sign.
- Choosing a spot without checking the property line, utilities or other detached signs on the same frontage.
- Deciding to add lighting after the permit was submitted as an unlit sign.
- Applying before the Certificate of Occupancy is approved.
- Hiring an installer who is not registered with the city.
- Forgetting the landscaping and irrigation that will grow around the base.
Starting a monument sign with us
If you are planning a monument sign in Dallas, send me photos of the entrance from the street in both directions, the property address, the logo file and whether you own or lease. If you lease, include the landlord's sign criteria if you have them.
From there, we schedule the survey, develop the design, handle the permit and coordinate fabrication and installation, so one team is accountable from artwork to the finished sign. My guide on questions to ask a sign company before hiring lists what you should expect to hear from any company you talk to, including us.
Questions people ask me
Can a monument sign be changed when tenants change?
Yes, if it is designed for that from the start. Multi-tenant monument signs often use separate panels that can be replaced when a tenant moves out, without rebuilding the structure. The City of Dallas sign page says changing the words on an interchangeable sign does not need a permit, but a new or re-faced sign meeting the permit conditions does, so ask before swapping a full face.
Does a monument sign have to be lit?
No. FASTSIGNS describes monument signs as lit or unlit. Lighting makes the sign readable after dark and in winter evenings, but it adds electrical work, a permit condition in Dallas and ongoing power. Businesses that close at dusk, or properties with good parking lot lighting, often choose an unlit sign with high-contrast lettering instead.
Who owns a monument sign on a leased property?
That depends on the lease. On many multi-tenant properties the landlord owns the structure and the tenant pays for its own panel, while a single-tenant lease may let the tenant build and own the sign. Read the sign section of the lease and the landlord's sign criteria before you order anything, and ask who is responsible for repairs and removal.
What file should I send for my logo?
A vector file, such as an AI, EPS or PDF exported from the original design software, gives the cleanest result at large sizes. A small image copied from a website usually turns blurry when enlarged to sign scale. If you do not have a vector file, a sign company can often redraw the logo, which adds a design step to the schedule.
Can I put a monument sign close to the street?
Placement depends on setbacks, the property line and the right-of-way. The City of Dallas sign page lists different setbacks for single-tenant and other monument signs, and signs in or over a public roadway trigger a permit on their own. A site survey before design is the reliable way to find a spot that is both visible and allowed.
Sources
Keep reading
More from Huzeifa
- Digital sign or printed sign: when a screen pays off for a Dallas business
- ADA signs for an office or store: which rooms need them and where they go
- What signs help visitors find reception from the parking garage?
- Window decals, banners, a wall sign: what you can install yourself and what you should not
Running a business
- Business Consultant · Armando
- Business Broker · Michael
- Franchise Consultant · Avinash
- Recruiting and Staffing Services · Chase
- Information Technology · Anthony
- Computer Software · Brandon