Fences & Decks · 7 min read
How long a new fence takes in Dallas, from the first visit to the final walkthrough
The building is the short part of a fence project. Here is what happens before the crew arrives, what the build days look like, and which delays a homeowner can actually prevent.
How long does it take to build a fence in Dallas?
Most residential wood and iron fences take my crew one to three days to build once the materials are on site. Masonry, large estate fences and automated gates take longer. What homeowners underestimate is the time before the first post hole: the estimate, the HOA review, a city permit when the fence needs one, and the utility locate. Those steps, not the carpentry, usually decide your finish date.
A fence project has two clocks. The build clock is short and predictable, because a crew that does this every week knows how many feet of fence go up in a day. The approval clock belongs to other people, including an HOA committee, a city office and the utility locators, and that clock is the one to start early.
Every written estimate from Park Cities Fence & Deck includes a timeline for the project. The timeline is specific to the yard, the material and the season. A general guide like this one tells you what the stages are, so the dates on the estimate make sense when you read them.
The four stages of a fence project
Our process has four stages, and every fence company's version looks similar. Knowing the order helps you see where your project is on any given day.
- On-site consultation. I walk the yard with you, measure the runs, look at the grade and the gates, and talk through material and design.
- Written estimate. You receive a free written estimate with the scope, the price and a timeline.
- Scheduling, permits and utility locates. We coordinate any city permit, the details your HOA needs and a free 811 utility locate before digging.
- Supervised installation and final walkthrough. An experienced team leader runs the build, and I walk the finished fence with you.
What has to happen before the first post hole?
Four things must be settled before anyone digs: the line, the approvals, the materials and the buried utilities. Skipping any one of them is how a three-day job turns into a three-week argument.
The line comes first. A fence company builds where the owner says the boundary is, and a survey is the definitive source for that boundary. If your survey is old, missing or disputed, sort that out before the estimate becomes a contract. A title officer's guide on what to do when a fence crosses the property line on a survey shows how expensive a misplaced fence becomes at resale.
The utility locate is the step people forget. The national 811 service says to contact 811 a few days before you plan to break ground, and that utility operators then send locators to mark buried lines with paint or flags. We place that request for our jobs, and the crew does not dig until the marks are down.
Materials are the last piece. Cedar pickets, posts and standard iron panels are normally easy to get in Dallas–Fort Worth. Custom iron, special-order gates, gate operators and masonry materials can take longer to arrive, and the build is scheduled around the delivery date.
Do HOA approval and a city permit add time?
Yes, and they are the two steps with the least predictable timing. An HOA reviews fence requests on its own calendar, and a city reviews permits on the city's calendar. Neither is controlled by the homeowner or the fence company.
In the City of Dallas, the permit question depends on height and location. The city's fence permit checklist states that a permit is required for fences exceeding 4 feet in height within a front yard or 6 feet in height in all other locations, and that the maximum allowable fence height is 9 feet. Applications are submitted online through DallasNow with a site plan and a drawing of the fence.
Some properties carry an extra review. The same checklist says proposed fences in conservation districts and historic districts require a Certificate of Appropriateness, and that a fence proposed within an easement needs written authorization from the utility company. Highland Park, University Park, Plano and the other cities we work in each have their own rules, so the answer for one address does not transfer to another.
The practical advice is to submit early and submit completely. We build to HOA specifications and provide the drawings and details the committee asks for. I cover the rules in more depth in my guide to fence permits and HOA approval in Dallas.
What the build days look like
Once materials are on site, the work follows the same order on nearly every wood or iron fence. A standard residential job moves through these steps over one to three days:
- Tear-out and haul-off of the old fence, if there is one, and clearing the fence line.
- Layout with string lines, marking post locations, gates and any steps in the grade.
- Digging post holes by hand near utility marks, then setting posts in concrete, plumb and in line.
- Hanging rails and pickets on a wood fence, or setting and fastening panels on an iron fence.
- Building and hanging the gates, then fitting latches and hardware.
- Trim, cap and kickboard where the design calls for them, followed by cleanup of the yard.
- The final walkthrough with the owner, checking the line, the gates and the finish.
Which fences take longer than three days?
Masonry, long runs and automation take longer. Our own FAQ says masonry, large estate fences and automated gates run past the one-to-three-day range that fits most wood and iron jobs.
Masonry is slower because of the sequence. Brick and stone fences and columns need footings, the masonry work itself and time for each stage to set before the next one loads it. A combination fence, with masonry columns and wood or iron panels between them, is scheduled as two trades in a row.
Automated gates add an electrical and controls stage. The gate has to be built and hung, the operator mounted, power brought to the opening, and the keypads, remotes and safety sensors installed and tested. My guide on adding an automatic driveway gate walks through that stage.
Site conditions stretch a schedule as well. A steep slope, rock, large tree roots along the line, a pool that must stay enclosed, or access through a narrow side yard all slow the daily footage. If you are still choosing a material, compare the options in my guide to wood, iron or masonry fences for a Dallas home.
What delays a fence, and which delays you control
Some delays belong to the weather, and others belong to decisions. North Texas storms and saturated clay can stop digging and concrete work for a day or more, and nobody can schedule around a storm that has not formed yet. The delays below are the ones a homeowner can prevent:
- An HOA application sent late or without the drawing, stain color or height the committee requires.
- A boundary question discovered on build day because no survey was available.
- A neighbor who shares the fence line and was not told the old fence was coming down.
- Design changes after materials are ordered, such as a different height, cap style or gate width.
- Sprinkler lines, dog runs, sheds or stored items left along the fence line.
- Pets and pool access that were not planned for the days the yard is open.
Can a fence project be sped up?
The build itself rarely needs speeding up, but the weeks before it often can be shortened. The fastest projects are the ones where the owner makes every decision once and hands over complete information at the start.
Decide the material, height, style and gate locations before you ask for estimates, so each company prices the same fence. Pull your survey and your HOA's fence rules before the consultation. Talk to the neighbors on shared lines early. If the fence is storm-damaged and the yard must be secured for a dog or a pool, say so at the first call, because a temporary panel or a priority repair may be possible while the full replacement is scheduled.
Price and schedule are linked. Custom details, special-order materials and masonry add time as well as cost, and my guide to what drives the cost of a new fence in Dallas explains each of those choices.
After the last picket: walkthrough, cure time and stain
The crew leaving is not the end of the timeline for a wood fence. I walk every finished job with the owner, and that walkthrough is the time to open and close each gate, sight down the top line and point out anything you want adjusted.
Stain comes later. New cedar should cure for several weeks to a few months before its first coat of stain, so the finish soaks in and lasts. We can stain the fence when the wood is ready or schedule that visit when the build is booked, and I explain the upkeep in my guide on making a cedar fence last in North Texas.
What to send for a timeline you can plan around
A useful timeline starts with a few facts. Tell me the address and the city, the approximate length of fence, the material you have in mind, how many gates you need, and whether an HOA is involved. Photos of the existing fence and the access to the back yard help. A copy of your survey helps most of all.
I attend every consultation myself, and the written estimate you receive includes the schedule along with the price. We serve Dallas, Highland Park, University Park and the surrounding cities, and the estimate is free. If you have a date in mind, such as a closing, a new puppy or a pool inspection, tell me at the start and I will say plainly whether the date is realistic.
Questions people ask me
Can a fence be built in one day?
A short, straightforward wood or iron fence on a flat lot can be finished in a day when the materials are on site and the old fence is already down. Park Cities Fence & Deck gives one to three days as the range for most residential wood and iron fences. Long runs, several gates, a slope or a tear-out push a job toward the longer end.
Do I need to be home while the fence is installed?
You do not need to be home for every hour of the build, but plan to be available at the start, when the layout and gate locations are confirmed, and at the end for the final walkthrough. Make sure the crew has access to the yard, water and power if needed, and that pets are kept indoors or away while sections of the fence are open.
Who calls 811 before a fence is built?
On our jobs, Park Cities Fence & Deck coordinates the free 811 utility locate before any digging. The national 811 service explains that the request goes to the utility operators, who send locators to mark buried lines with paint or flags. The service also advises against digging on top of or within 18 to 24 inches of the marks.
Does rain delay a fence installation?
Heavy rain can delay the digging and concrete stages, because post holes fill with water and saturated clay does not hold a clean hole. Light rain often does not stop carpentry on posts that are already set. Expect the schedule to shift by the length of the weather, and ask your fence company how it communicates a weather day.
What time of year is best to build a fence in Dallas?
A fence can be built in any season in Dallas. Spring storms bring both weather days and a rush of repair calls, so schedules tend to be fuller then. Planning a replacement before storm season, and starting any HOA application early, gives you the widest choice of dates. Stain timing depends on the wood curing, not on the calendar alone.
Sources
Keep reading
More from Jack
- The storm took down the fence: what Texas homeowners insurance usually pays, and what it does not
- Cedar or composite deck boards: which one suits a Dallas backyard
- How to close fence gaps for a dog in a sloped yard
- Can you build a deck over a cracked concrete patio?
Your home
- Roofing · Chris
- Gutters · Jordan
- Painter · Andrey
- Power Washing · Doug
- Foundation & Concrete · TJ
- Drywall Repair · John