Before a Texas homeowner can sue a builder or remodeler over defects, the Residential Construction Liability Act requires notice, an inspection window and a chance to make an offer. Skipping those steps can stall the case.
What Texas requires before you can sue a builder
Before you sue a contractor over defects in a home, Texas generally requires you to send written notice by certified mail at least 60 days before filing. The contractor then gets a chance to inspect and to offer a repair or settlement. Skip that process and the lawsuit can be put on hold, and how you answer the offer can affect what you recover.
I handle construction disputes under the Residential Construction Liability Act, the Deceptive Trade Practices Act, and trust fund and mechanic's lien law, and I served as Secretary of the Texas Residential Construction Commission's Arbitration Taskforce. In my experience, homeowners who treat the notice period as a strategy, not a formality, end up in a far better position.
What is the Residential Construction Liability Act?
The Residential Construction Liability Act, found in the Texas Property Code beginning at Section 27.001, sets the ground rules for claims against contractors over construction defects in residences. It applies to builders of new homes and to many remodelers, and it shapes the case before any petition is filed.
The idea behind the Act is simple: give the contractor a fair chance to see the problem and fix it before a court gets involved. The Act rewards the side that behaves reasonably during that window and penalizes the side that does not.
Texas once had a state agency for this as well. The Texas Sunset Advisory Commission records that the Texas Residential Construction Commission was abolished when its Act expired on September 1, 2009. Today the Property Code process, the contract you signed and the courts or arbitration carry the weight.
For the homeowner, the practical effect is that the first formal step in a defect dispute is a letter, not a lawsuit. How well that letter is written, and how carefully the next 60 days are handled, often decides whether the case settles with a real repair or turns into an expensive fight.
How much notice do you have to give, and what goes in it?
Texas Property Code Section 27.004 requires the homeowner to give written notice by certified mail, return receipt requested, to the contractor's last known address, before the 60th day preceding the lawsuit. In practice, that means the letter goes out at least 60 days before you file.
A useful notice letter describes each defect in reasonable detail, where it is in the house and when you first noticed it. Vague complaints such as poor workmanship give the contractor room to argue later that it never had a fair chance to respond. I recommend including or offering to provide photos, inspection reports and any engineer's findings.
Keep the green return receipt card or the online tracking record. If the contractor later claims it never received notice, that proof decides the argument. Texas Law Help gives the same practical advice for any contractor problem: follow phone calls with a certified letter and keep copies of everything.
- Each defect, with its location and when it appeared.
- Photos, dates and any written reports from inspectors or engineers.
- The contract, change orders and any written warranty.
- A request that the contractor respond under the Residential Construction Liability Act.
- Your contact information and times the house is available for inspection.
The 35-day inspection window
Once the contractor receives the notice, Section 27.004 gives it a 35-day period to request an inspection, and during that period the contractor may conduct up to three inspections. Refusing reasonable access can hurt the homeowner later.
Be present for each inspection, or have someone you trust there. Take your own notes and photos of what the contractor's people look at, open or test. If the contractor brings an engineer, ask for a copy of the report.
This is also the moment to get your own expert if the defect is structural, such as foundation movement, framing or water intrusion. The Act lists reasonable and necessary engineering and consulting fees among the damages a homeowner can recover, so a solid report is often worth having early.
Schedule the inspections promptly and confirm each date in writing. A record showing you offered several reasonable times is far more persuasive than a memory of phone calls if the contractor later says you made the house unavailable.
What happens when the contractor makes an offer?
The contractor may make a written settlement offer no later than the 60th day after receiving the notice. Under Section 27.004, the offer can include an agreement to repair the defects fully or partly, at the contractor's expense or at a reduced rate, and it must describe the repairs and the completion time if the work will take more than 60 days.
If you consider the offer unreasonable, you must tell the contractor in writing, with reasons in reasonable detail, on or before the 25th day after you receive it. The contractor then has 10 days after receiving that reply to make a supplemental offer. An offer not accepted before the 25th day is treated as rejected.
This is the step where homeowners most often hurt their own case. A short reply that just says no does not satisfy the statute, and silence counts as a rejection.
Read the offer as you would read a new contract. It should say who will do the work, what materials and methods they will use, when the work starts and ends, and what warranty covers the repair. If any of that is missing, ask for it in your written reply rather than guessing.
Can rejecting a repair offer limit what you recover?
Yes. If a court or arbitrator later finds the contractor's last offer was reasonable and you rejected it, Section 27.004(e) limits your recovery to the fair market value of that offer, plus costs and fees incurred before the rejection.
The reverse is also true. If the contractor fails to make a reasonable offer, that limit does not apply. That is why I look hard at every offer before advising a client to accept or reject it: Is the repair method sound? Is the scope complete? Does the timeline make sense? Will the same crew that caused the problem do the fix?
When the Act's limits do not apply, the economic damages it allows include the reasonable cost of repairs, the cost of replacing or repairing damaged goods, engineering and consulting fees, reasonable temporary housing during repairs, loss of market value for structural failures, and reasonable and necessary attorney's fees.
What if you have already filed, or time is running out?
If a lawsuit is filed without the required notice, the contractor can ask the court to abate it, which puts the case on hold until the notice process is completed. Under Section 27.004(d), an uncontested verified motion leads to automatic abatement beginning on the 11th day.
The statute does excuse advance notice when filing early is necessary to keep the limitations period from expiring, and in that situation the case is abated to allow the notice and offer steps to happen. Deadlines for construction claims depend on the type of claim, so talk to a licensed Texas attorney promptly. Tina Wysk's guide to how long you have to sue over a broken contract in Texas explains how the clock generally works.
Steps that protect your claim from the first day
Most construction cases are won or lost on records made long before anyone calls a lawyer. These are the habits I ask homeowners to start as soon as something looks wrong:
- Photograph each defect with a date, and again if it gets worse.
- Keep every text and email with the builder; a guide on preserving business texts and email explains how.
- Gather the contract, change orders, warranty, permits and payment records in one folder.
- Do not pay the final draw or sign a release while defects remain open.
- Do not let another contractor tear out the work before the original contractor has had its inspection.
- Ask about any liens filed on the property before you withhold payment.
Mistakes that weaken a homeowner's position
The most costly mistake is repairing everything first and sending notice afterward. If the contractor never had a chance to inspect, it will argue the Act's process was defeated, and the evidence is gone.
Other mistakes I see often: sending notice by regular email only, describing defects too vaguely, refusing a reasonable inspection, ignoring an arbitration clause in the contract, and rejecting an offer without written reasons. Many of these problems start before the job does, which is why Elliot Presser's guide to red flags before hiring a remodeling contractor in Texas is worth reading before the next project.
Finally, do not assume the case must end in court. Many contracts require arbitration, and many disputes settle once the Act's offer process has run. My guide to questions to ask a business attorney before hiring covers how to find counsel who can handle both paths.
Another common problem is letting frustration drive the correspondence. Angry emails, threats posted online and messages copied to neighbors rarely help, and they often show up later as exhibits. Keep every letter factual, specific and calm, as if a judge will read it, because one may.
How I help homeowners and builders in Dallas
I represent clients in construction disputes in Dallas and across Texas, including Residential Construction Liability Act claims, DTPA claims, and trust fund and mechanic's lien litigation. A first conversation usually covers the contract, the defects, what has been sent so far and where the deadlines stand.
Bring the contract, change orders, photos, any inspection or engineering reports and every letter exchanged with the contractor. This guide is general information, not legal advice. Talk to a licensed Texas attorney about how the Residential Construction Liability Act applies to your home and your contract.
Questions people ask me
Does the Residential Construction Liability Act apply to remodeling work, not just new homes?
The Act covers claims against contractors over construction defects in residences, and many remodeling and repair projects fall within it, not only new construction. Whether a particular job qualifies depends on the work performed, the type of property and the claims involved. Talk to a licensed Texas attorney before sending notice, because the answer shapes the letter and the timeline.
Can I hire a different contractor to fix the defect right away?
Emergency steps to stop ongoing damage, such as a tarp or shutting off water, are usually sensible. Tearing out and replacing the defective work before the original contractor has had its inspection opportunity can weaken a claim, because the evidence disappears. Document everything thoroughly, send notice, allow the inspection window, then decide on repairs with legal advice.
Does the contract's arbitration clause change the notice requirement?
Generally no. The Act's notice and offer process applies whether the claim ends up in court or in arbitration, and Section 27.004 refers to actions before a court or tribunal. The arbitration clause decides where the dispute is heard and often how fees are shared. The Act lists reasonable arbitration filing fees and the homeowner's share of arbitrator compensation among recoverable damages.
Can I still bring a Deceptive Trade Practices Act claim against a builder?
Sometimes. A builder's false or misleading statements can support a claim under the Texas Deceptive Trade Practices Act, but when the claim arises from a residential construction defect, the Residential Construction Liability Act's notice and offer process still has to be followed first. How the two statutes interact depends on the facts, so a licensed Texas attorney should review the claim before anything is filed.
What if the contractor ignores my notice letter completely?
If the contractor never requests an inspection and makes no reasonable offer, Section 27.004(f) says the Act's limits on damages do not apply. Keep proof of delivery and a record of the silence. After the 60-day notice period, the homeowner can generally proceed with a lawsuit or arbitration. An attorney can confirm the timing before anything is filed.
Sources
Keep reading
More from Steven
- Doing business under another name in Texas: when an LLC needs an assumed name certificate
- Asset purchase or stock purchase: two ways to buy a Texas business
- How two equal Texas LLC owners can plan for a deadlock
- Your LLC is not a force field: myths about personal liability protection in Texas
Legal and family matters
- Estate Planning Law · Marshall
- Family Law · Greg
- Litigation · Tina
- Mediator · John
- Personal Injury Attorney · Courtny