Renovations/Remodeling · 7 min read
Change orders and payment schedules on a Texas remodel: how to keep the price from growing
The price of a remodel moves for four reasons, and three of them can be controlled before work starts. The fourth needs a written process agreed in advance.
How do change orders and payments work on a remodel?
A change order is a written amendment to your remodeling contract. It describes what is changing, what it adds or subtracts from the price, and what it does to the schedule, and both sides sign it before the changed work starts. Payments should follow finished stages of work, with the last payment held until the job is complete. At Spire Construction I treat both rules as basic.
Homeowners in Dallas and Richardson often tell me the same story about an earlier project. The bid was one number, the final bill was another, and nobody could show them in writing where the difference came from. That is a process problem more than a pricing problem.
The fix is not complicated. Most of it happens before demolition, and the rest depends on a short written procedure that the owner and the contractor agree to follow when something unexpected turns up.
What is a change order, exactly?
A change order is the only proper way to alter the scope or price of a signed contract. A conversation in the kitchen is not a change order. A text that says go ahead is a start, but it is not one either, because it usually leaves out the price or the effect on the completion date.
A change order can raise the price, lower it or leave it the same. Swapping a tile for one that costs less should produce a credit. Deleting a built-in should too. If changes only ever move the price upward, ask why.
Whatever form the contractor uses, it should contain the items below. If one is missing, ask for it before signing.
- A plain description of the changed work and where in the house it applies
- The reason for the change: owner request, hidden condition, inspection requirement or unavailable material
- The price added or deducted, with labor and materials shown
- The effect on the completion date, stated in days
- The new contract total after the change
- Signatures and dates from the owner and the contractor before the work begins
The four places extra cost comes from
In my experience, nearly every increase on a remodel traces back to one of four causes. Knowing which one you are looking at tells you whether the increase could have been avoided.
The first three are within the control of the owner and the contractor before work begins. Only hidden conditions are a true surprise, and even those can be planned for. A contractor who has looked in the attic, under the sinks and at the electrical panel before pricing will find fewer surprises than one who priced from photos. Hidden conditions are most common in wet rooms, and I describe the usual warning signs in how to tell whether a tile shower is leaking behind the walls.
- Vague scope: the estimate said remodel the bathroom, and the two sides pictured different bathrooms
- Unmade selections: cabinets, countertops, tile, plumbing fixtures and lighting were left as allowances and the real choices cost more
- Owner changes during the job: moving a wall, adding outlets or upgrading a finish after work is under way
- Hidden conditions: rot, old wiring, leaking supply lines or framing problems that could not be seen until the walls were open
What should be decided before demolition starts?
Everything you can see and touch in the finished room should be chosen before the first wall is opened. That means cabinets, countertops, flooring, tile, plumbing fixtures, appliances, lighting, hardware and paint colors, each written into the contract by name or model.
An allowance is a placeholder amount for something not yet chosen. Allowances are sometimes necessary, but each one is an open question about the final price. Ask how each allowance was calculated and check it against the products you actually like before you sign. If the allowance would not buy the tile you have in mind, the contract price is already wrong.
Our process at Spire puts this step early. After the free consultation, we outline a timeline and budget and identify the material and design decisions to be made, then provide an upfront written estimate before construction. A Dallas interior designer makes the same point in a guide on why kitchen remodels stall before the wall comes down.
Comparing bids works the same way. If three contractors price three different sets of assumptions, the numbers cannot be compared, which I cover in our guide to comparing three remodel bids.
How should a remodel payment schedule be set up?
Payments should be tied to work that is finished and visible, not to dates on a calendar. A common structure is a deposit at signing, progress payments at defined stages, and a final payment after the walkthrough.
The Federal Trade Commission's guidance for homeowners is direct on two points. Do not pay the full amount for the project up front, and never make the final payment until the work is done and you are satisfied with it. The agency also notes that some states limit how much a contractor can ask for as a down payment.
Each payment stage should be something you can verify by walking through the house. Stages like the ones below are easy for both sides to confirm.
Change orders should be billed according to their own terms, stated on the change order itself. Mixing change order charges into regular progress payments without labeling them is how owners lose track of the total.
- Deposit at signing, to schedule the job and order long-lead materials such as cabinets
- Completion of demolition and rough framing
- Completion of rough plumbing, electrical and mechanical work, after any required inspections
- Drywall, cabinets and countertops installed
- Substantial completion: the room is usable and only minor items remain
- Final payment after the walkthrough list is finished
What does Texas law add when the house is your homestead?
Texas law adds paperwork requirements meant to protect homeowners. I am a contractor and not an attorney, so treat this as a description of what you should expect to see and ask a Texas attorney about your own contract.
Under Texas Property Code section 53.254, a contractor's lien on a homestead depends on a written contract that sets out the terms and is signed by the owner and the contractor before materials are furnished or labor is performed. If the owner is married, both spouses must sign.
Section 53.255 requires the original contractor to give the owner a disclosure statement before a residential construction contract is signed. The statutory statement advises owners to get the agreement in writing, including the work, the timing, the cost and the payment terms, and explains the owner's right to a list of subcontractors and suppliers.
The same part of the code describes funds an owner is expected to hold back for a period after completion. That holdback protects owners against claims from unpaid subcontractors and suppliers, and it should be reflected in the final payment terms. The warning signs to watch for in a contract are in our guide to red flags when hiring a remodeling contractor in Texas.
When the surprise is behind the wall
Hidden conditions are the one cause nobody can remove completely, especially in older North Texas homes. What you can control is how they are handled. Agree on the steps in the contract, before there is any pressure.
Some repairs cannot wait for a long discussion, such as an active leak. The contract should say what the contractor may do immediately to prevent damage and how that work is priced. Everything beyond stopping the damage should wait for a signed change order.
Hidden conditions sometimes change what a city inspector will require. If opened walls reveal work that must be brought up to code, the permit scope may change, which I explain in our guide on whether you need a permit to remodel in Dallas.
- Work stops in the affected area
- The contractor photographs the condition and shows the owner in person or by video
- The contractor explains the options, including the least expensive acceptable repair
- Each option is priced in writing with its effect on the schedule
- The owner chooses and signs a change order
- Work resumes
Mistakes that make a remodel cost more
Most of the overruns I am asked to explain on other contractors' jobs come from a short list of habits. Every one of them is avoidable.
Keep one folder, paper or digital, with the contract, every change order and every payment receipt. At any point in the job you should be able to add the original price and the signed changes and arrive at the same total as your contractor.
- Signing a contract with a one-line scope
- Accepting allowances without checking them against real products
- Approving changes verbally with a worker on site and not with the project manager in writing
- Changing selections after materials have been ordered
- Paying ahead of the work to help the contractor's cash flow
- Making the final payment before the walkthrough list is complete
- Keeping no running total of approved changes
How we handle pricing at Spire
Spire Construction is a Richardson-based general contractor that my partner Ryan Seale and I founded in 2017. Every project starts with a free consultation. We then put the plan on paper with a timeline and budget, list the material and design decisions, and give an upfront written estimate before construction begins.
During the work, our project managers check the site often and report progress, and the job ends with a final walkthrough with the owner. If something changes along the way, the change is described, priced and approved before we build it.
If you are planning a kitchen, a bathroom, an addition or a rebuild after water or fire damage, bring your wish list, any drawings and the selections you have already made. If you have a bid or a contract from another company, bring that too, and we can go through the scope, the allowances and the payment terms line by line.
Questions people ask me
Can a contractor charge more than the estimate without my approval?
That depends on what the contract says, which is why the change procedure belongs in writing. A well-written remodeling contract states that the price changes only through a change order signed by the owner. If your contract allows the contractor to bill extra work without prior approval, ask for that term to be revised before signing, and consult a Texas attorney if you are unsure.
How much should the deposit be on a remodeling project?
No single figure fits every job. A deposit reasonably covers scheduling and materials that must be ordered early, such as custom cabinets. The Federal Trade Commission advises homeowners not to pay the full project amount up front. Be cautious if a contractor asks for most of the price before any work or materials have arrived at the house.
What is the difference between an estimate, a bid and a contract?
An estimate is the contractor's projected cost for a described scope. A bid is an offer to do that scope for a stated price. A contract is the signed agreement that binds both sides. The Federal Trade Commission says a written estimate should include a description of the work, the materials, a completion date and the price. Confirm which document you are signing.
Should I set aside a contingency for a remodel?
Yes. Even with a tight scope, an older house can hide rot, outdated wiring or plumbing problems. Keep a reserve of your own, outside the contract, for hidden conditions and for upgrades you decide you want once the work is under way. Ask the contractor which surprises are most likely in a house of your age and construction.
Can I cancel a remodeling contract after signing it?
The Federal Trade Commission notes that a contract signed at your home, or somewhere other than the seller's permanent place of business, should include a written statement of your right to cancel within three business days. Beyond that period, cancellation depends on the terms of the contract. Read the cancellation section before signing and ask a Texas attorney about your specific situation.
Sources
Keep reading
More from Elliot
- Tub or walk-in shower: when the conversion makes sense and what the work involves
- Turning the attic into a bonus room or bedroom: what the space needs before it qualifies
- Can you stay in the house when your only kitchen is being remodeled?
- What a bathroom remodel costs in Dallas, and the choices that move the number
Your home
- Roofing · Chris
- Gutters · Jordan
- Painter · Andrey
- Power Washing · Doug
- Foundation & Concrete · TJ
- Drywall Repair · John