Moving Company · 7 min read
Moving the office without losing a workday: how a weekend relocation is planned
An office move is mostly a planning job. Done right, people pack their desks on Friday afternoon and log in at the new address on Monday morning.
Most of the downtime is decided weeks before the truck arrives
You avoid downtime by moving outside business hours, usually over a weekend or holiday, and by doing nearly all of the work in the weeks before: a single internal owner for the move, a floor plan for the new space, labels on every desk, crate and device, a data backup and an IT plan for the reconnect. Larger offices often move in phases, one department at a time, so part of the business is always working. Start planning six to eight weeks ahead.
We at IMS Relocation handle office and corporate relocations, along with moves for medical facilities, labs, schools, hotels and restaurants. The pattern is always the same. The moves that go smoothly are the ones where the planning was finished before moving day, and the ones that run into Monday are the ones where decisions were still being made while the crew was standing in the hallway.
A realistic timeline, working back from move day
We recommend at least six to eight weeks for commercial moves, and more for a large office or a facility with specialized equipment. That time is not for the movers; it is for the decisions only you can make. The earlier the estimate happens, the earlier you know what the move involves and what you need to settle internally.
If you are still deciding whether to move at all, that is a real estate question first. Commercial real estate broker Julie Smith has written about weighing a lease renewal against a move, which is the step before everything here.
- Eight weeks out: name an internal move lead, get estimates, confirm the move date with both buildings
- Six weeks out: finalize the floor plan, decide what furniture moves and what is replaced or discarded
- Four weeks out: schedule IT, telecom and internet at the new space; notify clients and vendors
- Two weeks out: deliver crates and labels, start packing files and storage rooms
- Move week: staff pack desks, IT backs up and powers down, crew moves after hours
- First workday: move team on site to fix anything out of place
One person inside the company has to own it
The single most useful thing you can do is name one person as the move lead and give them authority to make decisions. Without that, every question becomes a meeting, and small items like where the printer goes or whether the old conference table comes along pile up until moving day. On our side, a moving counselor works with that person from the estimate through the first day in the new space.
The move lead should also assign roles inside the company. Someone owns IT, someone owns communication with staff and clients, and each department has a contact who makes sure its area is packed and labeled. It also helps to review your lease obligations and utilities at both locations early, so nothing is shut off before you are out or missing when you arrive.
- Move lead: single point of contact with the mover and both buildings
- IT lead: backups, disconnect, reconnect and testing
- Department contacts: packing and labeling for their area
- Communications: staff updates, client and vendor notices, address changes
- Facilities: keys, access cards, parking, utilities and building rules
IT and data: the part that decides whether Monday works
Furniture can be put back in an hour. A server that will not come up can cost a day. Treat the technology plan as its own project. Back up everything off-site before the move. Label every computer, monitor, dock and cable so each one goes back to the right desk, and keep a list of what belongs where. Critical drives and anything holding sensitive data are best carried personally by someone on your team rather than placed on the truck.
Our crews disconnect and reconnect office technology and related equipment, and we can coordinate with your IT provider for anything beyond that, such as network setup, servers or phone systems. Larger companies should bring their IT people into planning from the start. If you do not have an IT provider, or yours is stretched thin, a managed IT firm such as Anthony Omini's team at Cross River Tech can own the network side while we handle the physical move.
Order internet service at the new address early. Installation dates can be the slowest part of the whole plan, and an office with desks, chairs and no connection is still closed for business.
Labeling and the floor plan do most of the crew's thinking
A good office move runs on a numbered floor plan. Every desk, office and room in the new space gets a number, and every crate, chair, monitor and piece of furniture going there gets a label with that number. The crew does not need to ask anyone where anything goes; they read the label and the plan. Inventory and label by department, and color coding by floor or wing makes it faster still.
Give each employee a short instruction sheet: what to pack, how to label it, what to take home and when their desk must be ready. Personal items, plants and anything valuable should go home with the employee. Files and shared storage rooms are usually the biggest job and should be packed by the people who know what is in them, or by our crew with clear instructions.
Furniture: move it, reconfigure it or leave it
Office furniture is where many companies discover the new space does not fit the old layout. Decide early which pieces move, which are replaced and which are sold, donated or discarded, because each choice changes the crew size and the schedule. Our crews handle the disassembly and reassembly of furniture, fixtures and equipment, along with furniture installation and custom crating for anything delicate.
If the new furniture is arriving from a vendor, coordinate the delivery so it is installed before your move or right after, not on the same night in the same freight elevator. If the new space is not ready when the old lease ends, commercial storage can hold furniture, equipment and records in the meantime. We also offer secure, confidential document storage, which helps if you are using the move as a chance to clear paper out of the office without destroying records you must keep.
After hours, weekends and moving in phases
The main tools for avoiding downtime are timing and sequence. We move offices outside business hours and on weekends, and holidays work well for larger moves because they add a day. Staff finish their work on Friday, pack their desks in the afternoon, and the crew starts once the office empties.
For a larger office, or one that cannot close even for a weekend, phasing is the answer. Departments move in a planned order over several nights or weekends, so part of the business is always working. Customer-facing teams and anything with regulatory or patient obligations usually move last or have a temporary setup, while back-office teams move first. Medical offices, labs and schools need their own sequencing because of equipment and safety requirements, and that is planned in detail at the estimate.
Building rules at both ends
Office buildings have rules that houses do not. Many set specific hours for moves, require freight elevators to be reserved, ask for protection on floors and walls, and require the mover to provide a certificate of insurance naming the building before the crew is allowed in. Get the rules from property management at both the old and the new building as soon as you have a date, and share them with your mover.
Loading docks and parking matter just as much. In busy parts of Dallas, a dock may be shared with other tenants or limited to certain hours, and street parking for a large truck may not be possible at all. These details shape the crew size and the schedule, and they are much easier to solve two weeks out than on the night of the move.
- Allowed move hours and days
- Freight elevator reservation and padding
- Certificate of insurance requirements
- Loading dock access and truck parking
- Floor, wall and door protection rules
- Key, badge and alarm access for the crew
What drives the cost of an office move
The main factors are the amount of furniture and equipment, how much disassembly and reassembly is needed, the distance, access at both buildings, the amount of packing our crew does versus your staff, and the timing. After-hours and weekend work is what keeps your business running, and it should be planned into the estimate from the start rather than added at the end. Specialized equipment, crating and storage are priced separately. Our guide to what drives the cost of a move explains each factor in more detail.
We give a written, upfront estimate after a walk-through of the space, in person or by video, so you can budget before you sign anything. For a small office, a portable storage container can also be a practical option; our 16-foot containers work well for offices of about 1,500 square feet.
Your first morning in the new space
Plan to have the move lead, an IT person and a crew contact on site when staff arrive on the first day. Small things always come up: a monitor at the wrong desk, a chair in the wrong room, a printer that needs a driver. Fixing them in the first hour keeps them from becoming a lost morning. Walk the space the evening before with your move lead and check the floor plan against what is actually in place.
Afterward, we follow up to make sure everything arrived as it should and to put right anything that did not. If you are planning a move in Dallas–Fort Worth and want to know what is realistic for your timeline, start with an estimate early, and read our guide on choosing a move date around peak season if your lease gives you some flexibility.
Questions people ask me
How far ahead should we plan an office move?
We recommend at least six to eight weeks for commercial moves, and more for a large office or a facility with specialized equipment. Most of that time goes into internal decisions such as the floor plan, IT and furniture, which the movers cannot make for you.
Can movers move our office over a weekend?
Yes. We move offices outside business hours and on weekends so staff can finish on Friday and work on Monday. Larger offices may move in phases over several nights or weekends to keep part of the business running.
Do movers disconnect and reconnect computers?
Our crews disconnect and reconnect office technology and related equipment. Back up your data off-site first, have someone on your team carry critical drives personally, and involve your IT provider for servers, networks and phone systems.
What if our new office is not ready when the old lease ends?
Furniture, equipment and records can go into commercial storage until the new space is ready, then be delivered on the date you choose. Plan that at the estimate so the storage and delivery are priced as one job.
Sources
Keep reading
More from Mike
- What a move really costs in Dallas: the six things that set the price
- Something arrived broken or did not arrive: how a moving damage claim works in Texas
- Pack it yourself or let the movers pack: where the savings are real and where they are not
- Moving in a Dallas summer: peak season, heat and how to pick your date
Buying, selling and moving
- Residential Real Estate · Andy
- Residential Mortgages · Maria
- Title Services · Gail
- Residential Property Management · Justin
- Airbnb & Short-Term Rental Management · Anna
- Commercial Real Estate · Julie