Commercial Builder · 7 min read
Lump sum, cost-plus or GMP: choosing the contract for a commercial build-out
The contract type decides who carries the risk when costs move. Pick it by how complete your drawings are and how much price certainty you need.
Lump sum, cost-plus or GMP: which contract fits a build-out?
It depends on how complete your drawings are and how much price certainty you need. A lump sum fits a project with finished drawings and a fixed scope. A guaranteed maximum price fits a project that has to start before design is final but still needs a ceiling. Open cost-plus fits only when nobody can define the scope yet. I help owners pick before the first number is written.
At Harrison Construction, we build tenant finish-outs, freestanding restaurants, medical and dental offices, retail and convenience stores across Dallas–Fort Worth and other states. The contract form is one of the first decisions an owner makes and one of the least understood, so here is how the three compare.
What is a lump sum contract?
A lump sum, also called a stipulated sum, is a single fixed price for a defined scope of work. The American Institute of Architects publishes the most widely used form, AIA Document A101, for use where the basis of payment is a stipulated sum, meaning a fixed price.
The contractor carries the risk of cost overruns within the defined scope. If the work costs more than estimated, the contractor absorbs it; if it costs less, the contractor keeps the difference. The owner pays more only when the scope changes through an approved change order.
AIA's own guidance points out that a fixed price works best when the owner has a clear scope and complete design at signing. For small, short projects, AIA offers a separate stand-alone form, A105, built for work that is modest in size and brief in duration.
The weakness of a lump sum is that it is only as good as the scope behind it. Anything missing from the drawings is not in the price. On a tenant finish-out, that often means items such as existing ceiling conditions, landlord-required upgrades or utility work outside the suite, which then return as change orders once construction starts.
What is a guaranteed maximum price contract?
A guaranteed maximum price, or GMP, contract pays the contractor the actual cost of the work plus a fee, with a ceiling the total cannot exceed except through approved changes. AIA Document A102 is the standard form, and AIA describes it as appropriate for large projects that require a guaranteed maximum price.
AIA's summary of A102 makes one point every owner should understand: the only value the contractor guarantees is the guaranteed maximum price itself. Individual line items on the schedule of values can run over, as long as the total stays under the ceiling.
Many GMP contracts also address what happens to savings if the final cost lands below the ceiling, either returning them to the owner or sharing them by an agreed formula. That clause is negotiated, not automatic, so read it before you sign.
A GMP also changes what the owner sees. Because the cost of the work is reimbursed, the owner or the owner's representative can review subcontractor bids, invoices and the contingency balance as the job moves. That visibility is a large part of the value, but only if someone on the owner's side actually reads the reports each month.
What is an open cost-plus contract?
Cost-plus without a cap pays the contractor's actual costs plus a fee, with no guaranteed ceiling. AIA's A103 form is written for projects where the cost is not fully known when construction starts.
This structure suits genuinely uncertain work: emergency repairs, renovations where existing conditions are hidden behind walls and above ceilings, or phased work whose scope is still being decided. The owner gains flexibility and full visibility into costs, and gives up top-end price protection.
AIA notes that both A102 and A103 are not intended for competitive bidding. In practice, cost-plus work is usually negotiated with a contractor the owner already trusts, which makes the choice of contractor even more important.
The three compared side by side
Each form moves risk to a different place. Here is the short version I give owners when they ask:
- Lump sum: best when drawings are complete; contractor carries cost risk inside the scope; owner sees the price, not the underlying costs; changes are priced one by one.
- Guaranteed maximum price: best when the schedule requires an early start; costs are open book; contractor carries risk above the ceiling; savings depend on the contract terms.
- Open cost-plus: best when scope cannot be defined; costs are fully visible; owner carries the risk of overruns; requires close monitoring and trust.
- Competitive bidding: works naturally with lump sum; GMP and cost-plus are typically negotiated.
How design status drives the choice
The most practical way to choose is to look at where the drawings stand. If the architect has finished construction documents and the landlord has approved them, a lump sum bid gives you a firm number to plan around. Our guide on whether to hire the architect or the contractor first explains how that sequence affects pricing.
If the lease clock is running and you need to start demolition or long-lead orders before every detail is drawn, a GMP lets the contractor price what is known, carry allowances for what is not and commit to a ceiling. Restaurants are a common case, because equipment, hoods and grease interceptors drive both the schedule and the budget.
If you are taking over a second-generation space where the condition of existing systems is unknown, some of the work may need to be priced as it is uncovered. That is where cost-plus, or a GMP with clear allowances, protects both sides better than a lump sum padded for unknowns.
Whatever the form, the number should rest on a clear list of what drives the cost. For restaurant owners, our guide to what drives the cost of a restaurant build-out shows which items are usually still moving when the contract is signed, and which ones belong in allowances instead of a firm price.
Does my lender care which contract I sign?
Often, yes. A construction lender wants to know the project can be finished within the budget it is financing. The Office of the Comptroller of the Currency notes that a bank can reduce the risk of cost overruns by requiring a fixed-price contract, and that when the borrower and contractor are related, the contract should be cost plus a fee with a guaranteed maximum price.
If your build-out is financed, ask the lender early which contract forms it accepts and what it requires for draws. The same applies to landlords funding a tenant improvement allowance; our guide to how a tenant improvement allowance is paid covers the paperwork that ties the contract to the money.
Multi-location brands raise a related question. When the same prototype is built in several cities, owners often prefer a consistent contract form and reporting package across every site, so budgets and change orders can be compared from one store to the next.
How do change orders work under each contract?
Under every form, a change in scope means a change order, and the change order should be priced and approved before the work is built. That is a rule we follow on our projects, because an unpriced change is where most budget disputes begin.
Under a lump sum, each change is priced as an addition or deduction to the fixed price. Under a GMP, approved changes adjust the ceiling, and the cost of the work is tracked open book. Under open cost-plus, changes simply add cost, which is why owners on that form need regular, detailed cost reports.
Allowances deserve special attention. An allowance is a placeholder amount for an item not yet selected, such as finishes or fixtures. When the real selection costs more, the difference is a change. Ask how every allowance in a bid was set, and whether it is realistic for what you want.
Mistakes owners make with build-out contracts
Most contract problems come from a mismatch between the form and the state of the project. These are the ones we see most:
The fix for almost all of them is the same: decide the contract form after you know how complete the drawings are, read the exclusions and allowances line by line, and make sure every bidder priced the same scope. A number that looks low because something was left out is not a savings.
- Signing a lump sum on incomplete drawings, then paying for every gap through change orders.
- Treating a GMP as a fixed price and not reviewing what is inside the allowances and contingency.
- Choosing open cost-plus without a plan for reviewing costs every month.
- Comparing bids from contractors who priced different scopes, then picking the lowest number.
- Leaving the savings clause, the fee definition or the treatment of contingency vague in a GMP.
- Starting work on verbal changes before they are priced and approved in writing.
How we price a build-out
We start with a site visit and a review of the documents, then prepare a conceptual estimate from early drawings and value-engineer options before permits. As the drawings mature, we bid the work with qualified subcontractor pricing. That process is described in detail in what happens in commercial pre-construction, and it is what gives an owner a reliable basis for any of the three contract forms.
During construction, owners receive electronic progress reports and open communication about budget, schedule and obstacles. If you are comparing contractors in Fort Worth, Dallas or another market, our list of questions to ask a commercial contractor before hiring will help you compare their contract terms as well as their prices. For the legal terms of any construction contract, talk to a licensed attorney before you sign.
Questions people ask me
Is a lump sum contract always cheaper for the owner?
Not necessarily. A contractor pricing a fixed sum on incomplete drawings has to include a cushion for unknowns, and the owner pays that cushion whether or not the risks appear. When drawings are complete, a lump sum can be very efficient. When they are not, a GMP with open-book costs can end up lower.
What is a contractor's fee in a cost-plus or GMP contract?
The fee is the contractor's compensation for overhead and profit, added to the cost of the work. It can be a percentage of cost, a fixed amount or another agreed formula. The contract should define exactly which costs are reimbursable and which are covered by the fee, because unclear definitions cause most cost-plus disputes.
Can a GMP be set before the drawings are complete?
Yes, that is often the reason to use one. The contractor prices the known scope, carries allowances and contingency for what is still undecided and commits to a ceiling based on stated assumptions. AIA's A102 form notes that those assumptions may require revisions to the contract documents, so list them clearly in the agreement.
Who keeps the savings if a GMP project comes in under budget?
That depends on the contract. Some GMP agreements return all savings to the owner, while others share them between owner and contractor by an agreed percentage to reward efficient work. If the contract is silent, the answer may be unclear, so negotiate and write the savings terms down before construction begins.
Do I need an attorney to review a construction contract?
For a commercial build-out, an attorney's review is a sensible step, especially for payment terms, change orders, warranties, liens and dispute resolution. Standard forms such as the AIA documents are widely used, but they are often modified. A contractor can explain how the pricing works; legal advice should come from a licensed attorney.
Sources
Keep reading
More from Lonnie
- Building a commercial kitchen: the hood, fire suppression, grease interceptor and everything behind the line
- The landlord offered a tenant improvement allowance: what it covers and how you get paid
- Can you remodel an office while the people in it keep working?
- What pre-construction really is, and why it decides the project before anyone builds
Running a business
- Business Consultant · Armando
- Business Broker · Michael
- Franchise Consultant · Avinash
- Recruiting and Staffing Services · Chase
- Information Technology · Anthony
- Computer Software · Brandon